JSP Lifestyle Home Solutions (Private Limited)

Waterborne Coatings Application for MARQ2 Project - Bangalore





Safety Procedure






  • All JSP applicators will wear only JSP branded t-shirts & helmets for easy identification
  • Provision of sufficient lighting / illumination of work area
  • Warning signs will be displayed around the JSP allotted work areas
  • JSP Electrician at site at all times - Electrical point to tap from client specified location
  • All JSP Application team members personal and health records will be kept at the site
  • JSP well trained supervisors will be at site at all times to ensure correct methodology followed
  • JSP well trained team only will carry required equipments and specified paint brushes
  • JSP Team will cover the floor around application area to protect before activity

Site Survey

  • JSP Team will store the products in rooms with temperarture between 5'C and 35'C
  • JSP Team will ensure that the room temperature of atleast 15'C, Films created at temperature below 15'c exhibit chemical and mechanical resistance properties below the commonly achieved standards
  • JSP Team will dispose Coating residues (washing water, booth water, used coating) in accordance with the site SOP's
  • JSP Team will check the completion of all civil works such as wall plastering, flooring and etc, within the apartment and in the corridor area in all aspects including 01 coat of wall paintinting to ensure that, there's no dust while application and drying perio 2-4 hours
  • JSP Team will provide a further list on obstruction materials if any to be removed prior to mobilizaion, since waterborne coatings need cross ventilation for quick drying and proper hardness films to be formed

Quality Control Methodology

  • JSP Quality & Compliance team will ensure that the Standard procedures are followed in selecting right the staining system to match the substrate depending on area of application and area of usage
  • JSP QA Team will inspect and approve before any over coating to ensure the required total Curing time of the coatings is ADHERED TO:
  • JSP QA Team will inspect the final coating to ensure total curing time is given in order to build expected Hardness and Chemical resistance

Execution Plan

  • JSP will provide an Execution Plan based on the Expected completion dates, based on clearence of apartments block wise and floor wise
  • JSP will time to time increase / decrease man power according to site requirement and handing over deadlines
  • JSP Team will do a sample and with the slected materials and will obtain client approval before application
  • JSP Team will execute work with 7-10 days, only receipt of Official WORK ORDER and advance payment

Surface preparation

  • JSP Team will carefully clean the surface of the wood, which is to be well dried (14-16% humidity and free from grease, wax or resin traces
  • JSP Team will do progressive sanding - 80 - 120 -180 grit sanding papers
  • JSP Team will apply matching water based putty made in Italy, after 120 grit sanding
  • JSP Team will sand with 180grit paper

Brand & Product details

AM0549/85 Stain

  • Waterborne protective wood stain Teak Colour to match the wood colour
  • it's a clear waterborne protective wood stain for hardwoods rich in extractives. Its tested formulation allows woods
  • woods preservation without the need of barriers, wthout problems of flow and with a little fibre raising

AZ3230/85

  • Hydroplus Waterborne Top Coat - Durability of these products on outdoor and joinery is superior, unlike solvent
  • products, waterborne products maintain their elasticity over time, which allows the coating's film to to follow the wood's
  • movement without cracking or flaking as well as water resistance

Stain Application

JSP will apply Hydroplus protective wood stain of Exterior Grade, Solid content 9, viscosity 48'


Area of Use

Door, doors frames and window frames

Drying time

Touch dry

60 mins

Through dry

4 hours

Overcoatable

16 hours

Application weight

150 to 300 microns

No.of coats

02 max

Top Coat Application

JSP will apply Hydroplus high solids waterborne Thixotrophic Clear Top Coat for Exteriors - is a one-pack waterborne topcoat with excellent elasticity and durability characteristics - It is specially formulated to provide such characteristics as flow, transparency ans water resistance


Area of Use

Door, doors frames and window frames

Drying time

Touch dry

01 - 04 hours

Through dry

01 - 08 hours

Overcoatable

24 hours

Application weight

150 to 300 microns

No.of coats

02 coats after sanding the 01st coat with 320 grit sand paper

Drying time

Waterborne products in must be dried in rooms with temperatures no lower than 15'C and relative humidity no greater than 85%

House Keeping

  • JSP Team will ensure on completion of application, the entire debris will be removed and moved to the specified area
  • JSP Team will handover applied doors to the CLIENT for installation